We are three weeks from closing!!! There are still so many things that have to be done inside the home but PM and PS assured us that we will definitely close on June 24th. We visited the house at least 3 times the past week and here are some photo updates from the past week. The brick facade has been completed. The interior has been drywalled and a first coat of paint has been applied. Our cabinets, sinks, mailbox and interior doors have also arrived and are now in the garage.
![]() |
| The brickwork is complete. All exterior doors and windows installed. The boxes in the front are the pebble clay siding. |
I really like the Savannah moss and it's great that even though there are 4 or 5 (?) Palermos on our street (only one with the same elevation as ours), all our Palermos look different from each other and our house is the only one with a full brick facade.
![]() |
| Garage doors are installed! |
![]() |
| Goodies in the garage. |
![]() |
| Painted walls. Pantry and door to basement. |
![]() |
| Plumbing work has also been done in the front of the home. Seems very shallow. |
Now here are some issues that we have emailed our PM about:
![]() |
This shouldn't hold water in it, should it?
The picture below shows plumbing lines that were run under the joists, which will be in the way when we finish our basement ceiling. This issue has been raised to my PS before and he said that he will make the plumbers run the lines through the joists, instead of under them. But they still have not fixed these as of yesterday.
The next few pics show gaps between the floor and the walls. These are found in bedroom 3 and the master closet. I am aware that they will be covered in vinyl siding eventually but I think these gaps should still be sealed.
Lastly, not just in the angle in this photo but we looked closely at our kitchen bar and it seems leaning to the right. So we asked our PM to make sure it is straight.
Some other issues that we mentioned to our PM are squeaking windows and floors. Maybe it's too early to complain about these, I don't know. Another disappointment is that I requested our PS several times about extra studs/TV brackets and extra joists under the laundry room. We have been assured multiple times that they will be done but were not and it's too late to do it, so that was really annoying.